A construction company will be penalized each day of delay in construction for bridge. The penalty will be $4000 for the first day and will increase by $1000 for each following day. Let f(n) be the amount penalized for the nth day. How much will the company owe if they are delayed 12 days?

asked
User Shryme
by
8.8k points

1 Answer

6 votes

Answer:

15,000 total, 4000 day 1, then 1000 for day 2 thru 12.