The graph below shows a line of best fit for the number of workers needed for different construction projects.

The equation for the line of best fit is shown below.



Based on the line of best fit, what is the expected time for completion with 14 workers on the project?
A.
7.5 days
B.
8.5 days
C.
12 days
D.
10 days

The graph below shows a line of best fit for the number of workers needed for different-example-1
asked
User Ede
by
7.7k points

1 Answer

4 votes

Answer:

D. 10

Explanation: