A can do a job in 4 days, and B in 9 days.

(i) How long will they take to complete the job together?
(ii) If they are paid 900 for the job, what will be each person's share?

asked
User Ndim
by
8.3k points

1 Answer

4 votes

Answer:

(i) (x/4) + (x/9) = 1

9x + 4x = 36

13x = 36

x = 2 10/13 days = about 2.77 days

(ii) A's share: $900(9/13) = $623.08

B's share: $900(4/13) = $276.92