if 30 assemblers can complete a certain job in 6 hours, how long will the same job take if the number of assemblers is cut back to 18

1 Answer

5 votes
Here is the answer to the question:
if 30 assemblers can complete a certain job in 6 hours, how long will the same job-example-1