The last three agile iterations showed a trend of increasingly prolonged test work.Which activity should the project manager plan to address the root cause? Select one: a. Adopt test automation tools b. Plan an iteration of testing only c. Plan more backlog refinement d. Practice a paired testing policy

1 Answer

6 votes

Final answer:

The project manager should adopt test automation tools to address the root cause of the prolonged test work in the last three agile iterations.

Step-by-step explanation:

The project manager should plan to adopt test automation tools to address the root cause of the increasingly prolonged test work in the last three agile iterations. Test automation tools can help streamline the testing process, reduce manual effort, and increase efficiency. By automating tests, the project team can identify and rectify any issues more quickly, enabling faster feedback and shorter testing cycles.