Final answer:
To draw a bill of materials for the stool, we need to identify the components and their lead times. The calculated quantities for each component are: 300 stools, 300 bases, 300 seats, 600 bolts, 1200 legs, and 1500 screws. The output of the MRP run would include these quantities.
Step-by-step explanation:
To draw a bill of materials for the stool, we need to identify the components and their lead times. From the given information, the bill of materials for the stool would include:
- Base (4 legs and 4 screws) with a lead time of 1 week
- Seat with a lead time of 3 weeks
- Bolts with a lead time of 2 weeks
To calculate the number of each product needed to meet the production schedule, we add up the quantities for each component:
- Stools: 100 in week 5 + 200 in week 7 = 300 stools
- Bases: 300 stools × 1 base/stool = 300 bases
- Seats: 300 stools × 1 seat/stool = 300 seats
- Bolts: 300 stools × 2 bolts/stool = 600 bolts
- Legs: 300 bases × 4 legs/base = 1200 legs
- Screws: 300 bases × 4 screws/base + 300 screws = 1500 screws
The full MRP (Material Requirements Planning) lists the quantities needed for each component based on the production schedule. The output of the MRP run would include:
- 300 stools
- 300 basesa
- 300 seats
- 600 bolts
- 1200 legs
- 1500 screws