Which of the following might the Scrum Team discuss during a Sprint Retrospective?

A. Methods of communication.
B. The way the Scrum Team does Sprint Planning.
C. Skills needed to improve the Development Team's ability to deliver.
D. Its Definition of Done.
E. All of the above.

asked
User Vadimich
by
8.1k points

1 Answer

2 votes

Final answer:

During a Sprint Retrospective, a Scrum Team might discuss various aspects such as methods of communication, Sprint Planning processes, skills needed for improvement, and their Definition of Done. This discussion aims to enhance the team's future performance and effectiveness.

Step-by-step explanation:

The Scrum Team might discuss a variety of topics during a Sprint Retrospective that aim to improve its effectiveness and efficiency in future sprints. Some of the typical areas for discussion include:

  • Methods of communication within the team.
  • The process and effectiveness of Sprint Planning.
  • The skills that are needed to enhance the Development Team's capability to deliver quality work.
  • Inspection and potential adaptation of the team's Definition of Done (DoD) to ensure it aligns with the current requirements.

The Sprint Retrospective is a key part of the Scrum framework where the team reflects on their performance and identifies areas for improvement. It covers all aspects of the Scrum Team's work, so the correct answer is E. All of the above.