When building a house, the number of days required to build is inversely proportional to with the number of workers. One house was built in 64 days by 12 workers. How many days would it take to build a similar house with 48 workers?

1 Answer

4 votes

Answer:

18

Explanation:

So if it took 64 days with 12 workers and they want to build a similar building with 48 this js what you would do.

12 workers took 64 days ok

now times that by 2

24 workers now divide the days cause you have 2x the workers

24 workers is 32 days

now do the same thing

times 2 workers divided 2 days

48 workers 18 days