You are the project manager for the construction of a chemical depository. Local residents oppose your project and have threatened to fight you in court. Ultimately, you decide to persuade your management to move the project to another town. What sort of risk response is this?

asked
User Shas
by
7.4k points

1 Answer

2 votes

Answer:

Avoid Response

Step-by-step explanation:

Because you are trying to remove the risk or remove yourself from the situation. Avoiding response is always about removing the threat by any means, and this can mean changing your project plan to avoid the risk because it’s detrimental to the project.