a contractor hired 150 men to pave a road in 30 days. how many men will he hire to do the same work in 20 days

asked
User Lucrezia
by
7.9k points

1 Answer

3 votes

Answer:

  • 225 men

----------------------

Find the amount of work in man*days and then divide the result by 20:

  • 150*30/20 =
  • 225

Hence the same work will be completed by 225 men.