What is true concerning the traditional role of a project manager (PM) and a Scrum master (SM)? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) check all that apply

a The SM has direct authority over the work.
b The SM is much more dominant than a PM.
c The PM develops the project plan.
d The SM facilitates the scrum process and resolves impediments at the team and organizational levels.
e The SM is more of a coach than a manager.

1 Answer

4 votes

Answer:

The correct options are c, d, and e.