A planning poker session results in the following estimates from the 5 members of the development team: 1, 5, 5, 5, and 8. What will be the next step?

Allow the team members who had extreme score to explain their view point and redo the estimation process until consensus is achieved.

Take the average of all the five numbers and calculate the story point as 4.8.

Take the majority choice and decide that the user story will be scored as 5 points.

Assign 8 story points to the user story to be on the safe side and not have time over runs.

1 Answer

3 votes

Final answer:

After planning poker results in a spread of estimates, allowing team members with extreme scores to explain their reasoning and working towards consensus through further discussion is the appropriate next step.

Step-by-step explanation:

The next step after a planning poker session results in estimates from the development team members of 1, 5, 5, 5, and 8 is to allow the team members who had extreme scores to explain their viewpoints and redo the estimation process until consensus is achieved. This is considered a standard practice in Agile methodologies and promotes team collaboration and understanding. It ensures that all perspectives are considered, and the team agrees upon a reasonable estimate for the user story based on their collective knowledge and experience.

answered
User AGill
by
8.5k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.