For all Hot Work, inspections must be completed_______ after completion of torch operations.

asked
User JRG
by
8.6k points

1 Answer

4 votes

Final answer:

Hot Work inspections should be carried out 30 minutes after the completion of torch operations to ensure safety and the prevention of fires.

Step-by-step explanation:

For all Hot Work, inspections must be completed 30 minutes after completion of torch operations. This is a safety procedure to ensure that there are no residual sparks or embers that could potentially cause a fire after the torch has been used. The area must be checked for safety and to confirm that all precautions were effective in preventing any risks of fire.