asked 62.6k views
1 vote
Adding to the project after it has already begun without making adjustments to time, cost, or resources, is known as:

a. scope creep
b. risk
c. milestones
d. acceptance criteria

asked
User Alanc
by
8.2k points

1 Answer

2 votes

Final answer:

Scope creep is when additions are made to a project without adjusting time, cost, or resources.

Step-by-step explanation:

Adding to a project after it has already begun without making adjustments to time, cost, or resources is known as scope creep. Scope creep refers to the uncontrolled expansion of a project's scope, which can lead to delays, increased costs, and resource constraints. It can occur when additional requirements or features are added to a project without proper planning or consideration.

answered
User Neelsg
by
7.9k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.