Final answer:
The reorder point of the production store is 116.5 units.
Step-by-step explanation:
The reorder point of the production store can be calculated using the formula:
Reorder point = (Average usage) + (Z-Score * Standard deviation)
In this case, the average usage is 100 units and the standard deviation is 10 units. With a 95% confidence level, the Z-Score is approximately 1.65.
Using these values, the reorder point can be calculated as:
- Reorder point = (100) + (1.65 * 10)
- Reorder point = 100 + 16.5
- Reorder point = 116.5 units