asked 68.3k views
3 votes
"Using the periodic review system the target level is:

A) forecast demand during the review period.
B) forecast demand during lead time.
C) the sum of A and B.
D) the sum of A and B plus the safety stock.
E) none of the above"

asked
User Msanders
by
8.7k points

1 Answer

0 votes

Final answer:

The target level in the periodic review system is the forecast demand during the review period.

Step-by-step explanation:

In the periodic review system, the target level is the forecast demand during the review period. This means that the target level represents the expected demand for a product or item during a specific time period when a review or evaluation is conducted. It does not include the forecast demand during lead time or the safety stock. Therefore, the answer is A) forecast demand during the review period.

answered
User St Mnmn
by
8.6k points

No related questions found

Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.