What is NOT part of the Scrum Product Backlog?

a) Detailed tasks
b) Recurring meetings like Daily Scrum
c) User stories
d) Tasks for exploration of features
e) Administrative tasks

asked
User LukeDuff
by
8.2k points

1 Answer

3 votes

Final answer:

The Scrum Product Backlog does not include detailed tasks or recurring meetings like Daily Scrum, but it may contain user stories, tasks for exploration of features, and administrative tasks depending on the project requirements.

Step-by-step explanation:

In Scrum, the Product Backlog is a prioritized list of features, bugs, technical work, and other requirements that need to be addressed in the project. It represents the vision and requirements of the product.

The tasks in the Product Backlog are generally high-level and not detailed, so option a) detailed tasks is not part of it. The Product Backlog may contain user stories (c), tasks for exploration of features (d), and administrative tasks(e), depending on the product and project requirements. However, recurring meetings like the Daily Scrum (b) are not included in the Product Backlog as they are part of the Scrum framework and not specific backlog items.

answered
User Swartzrock
by
8.7k points