asked 101k views
0 votes
If one of the constraints in the Golden Triangle, the scope, is increased, what is the best way to balance the triangle?

1) Increase the length of one of the other two sides
2) Decrease the length of one of the other two sides
3) Increase the angle opposite to the increased scope
4) Decrease the angle opposite to the increased scope

1 Answer

5 votes

Final answer:

The Golden Triangle in project management consists of scope, cost, and time. When increasing the scope, balance can be achieved by increasing either the cost or the time constraints.

Step-by-step explanation:

The question you have asked pertains to the concept of the Golden Triangle in project management, which is a visual representation of the relationship between three primary constraints: scope, cost, and time. When you mention increasing the scope within the Golden Triangle, it is necessary to balance the triangle by adjusting the other constraints. To balance the triangle when scope is increased, you typically have to either increase the cost (which means allocating more resources or funds) or increase the timeframe (which means extending the project deadline). Therefore, the best way to balance the triangle is by either increasing the length of one of the other two sides (cost or time) to maintain project equilibrium.

answered
User Vsarunov
by
8.3k points