Which of the following is not an advantage of a pure project?

A. Project manager has full authority.
B. Team members work on one project.
C. Shortened communication lines.
D. Increased flexibility in resource use.

1 Answer

5 votes

Final answer:

The correct answer is A. Project manager has full authority. A pure project is a type of organizational structure in which a project manager has full authority and control over the resources allocated to the project.

Step-by-step explanation:

The correct answer is A. Project manager has full authority.

A pure project is a type of organizational structure in which a project manager has full authority and control over the resources allocated to the project.

While this can be an advantage in terms of decision-making and accountability, it may also lead to challenges such as conflicts with other departments and lack of coordination with organizational goals.

In contrast, the advantages of a pure project include team members working on one project, shortened communication lines, and increased flexibility in resource use.