Which of the following would probably not involve the use of pert?

1) Project management
2) Critical path analysis
3) Time series analysis
4) Risk assessment

1 Answer

2 votes

Final answer:

Time series analysis is the choice that would probably not involve the use of PERT as it is a statistical method used for analyzing trends over time, while PERT is a project management tool used for planning large projects.

Step-by-step explanation:

The question which asks, "Which of the following would probably not involve the use of PERT?" is referring to Program Evaluation and Review Technique (PERT), which is a project management tool. Among the options provided:

  • Project management
  • Critical path analysis
  • Time series analysis
  • Risk assessment

Time series analysis would probably not involve the use of PERT because it is a statistical technique that deals with analyzing ordered series of data, often to understand or forecast trends over time. PERT, on the other hand, is typically used to plan and control large projects by analyzing the tasks involved and estimating the shortest project duration.