At a chemical factory, the basic week is 40 hours, during a particular week Mr. James earned a gross wage of $518.00, but $148,00 was for overtime. Calculate Mr. James' basic rate of payment

1 Answer

8 votes

Answer:

his basic wage is 370 dollars since 148 is for overtime. Just subtract from the gross wage, and that is your answer.