asked 78.4k views
3 votes
Which is not involved in a feasibility study?

a. technical analysis
b. financial analysis
c. organizational analysis
d. Inception

1 Answer

6 votes

Final answer:

The answer to the question is 'd. Inception'. Inception is not typically an analysis component within a feasibility study, but rather a phase in project development.

Step-by-step explanation:

The component not involved in a feasibility study is d. Inception. A feasibility study focuses on assessing the practicality and viability of a proposed project or system. Key analyses typically include technical analysis, which evaluates the technical resources and capabilities needed; financial analysis, which examines the economic aspects including costs, revenues, and profitability; and organizational analysis, which looks at the project’s impact on the organization and its fit within the current business structure. Inception, while it may be a phase in the project development process, is not an analysis component within a feasibility study.

answered
User Nicollette
by
9.4k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.

Categories