Answer:
the budgeted direct labor cost is $441,000
Step-by-step explanation:
The computation of the budgeted direct labor cost is shown below:
Budgeted direct labor cost 
 = Budgeted production × hours per unit × rate per hour 
 = 28,000 units × 1.5 × $10.50 
 = $441,000
Hence, the budgeted direct labor cost is $441,000
So the correct option is B.