asked 13.5k views
0 votes
Which of the following is NOT a configuration management activity associated with the Perform Integrated Change Control process?

A Configuration identification
B Configuration status accounting
C Configuration risk management
D Configuration verification and auditing

asked
User Ptha
by
7.8k points

1 Answer

2 votes

Final answer:

The correct answer to the question is 'C. Configuration risk management', as it is not a standard activity in configuration management and typically pertains to broader project risk management.

Step-by-step explanation:

The question asks which activity is NOT associated with the Perform Integrated Change Control process in configuration management. The listed activities are:

  • Configuration identification - Establishing and maintaining the consistency of a product's attributes with its requirements and product configuration information.
  • Configuration status accounting - Recording and reporting on the product's configuration and any changes to it.
  • Configuration risk management - NOT a standard activity in configuration management, as it typically falls under broader project risk management.
  • Configuration verification and auditing - Ensuring that the composition of a configuration item is known and that changes to it are systematically controlled.

Therefore, the correct answer to the question is C, Configuration risk management.

answered
User Bluesmonk
by
8.4k points

No related questions found