asked 141k views
3 votes
Vaughn has a standard of 2 hours of labor per unit, at 12 per hour. In producing 3400 units, Vaughn used 6400 hours of labor at a total cost of 78080. Vaughn's total labor variance is _______________.

asked
User Romsky
by
8.7k points

1 Answer

6 votes

Final answer:

Vaughn's total labor variance is $3,520.

Step-by-step explanation:

To calculate Vaughn's total labor variance, we need to determine the standard labor cost given the standard of 2 hours of labor per unit at $12 per hour. Then we can compare it to the actual labor cost.

  1. Calculate the standard labor cost: 2 hours per unit * $12 per hour = $24 per unit.
  2. Calculate the total standard labor cost for producing 3400 units: $24 per unit * 3400 units = $81,600.
  3. Calculate the labor variance: Total standard labor cost - Actual labor cost = $81,600 - $78,080 = $3,520.

Therefore, Vaughn's total labor variance is $3,520.

answered
User Oniropolo
by
7.7k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.