Ten men working 6 hours a day take 12 days to complete a job. How long will it take 8 men working 12 hours a day to complete the same job? (3mks)​

asked
User BlueNC
by
7.5k points

1 Answer

6 votes

Answer:

Explanation:

7 and 1/2 days