asked 146k views
1 vote
Please help! Thank you!

Please help! Thank you!-example-1

1 Answer

2 votes

Answer:

The answer is D, y=0.25t + 9.5

Explanation:

Since the crew has been painting at a rate of 0.25 per hour continuosly, it will be 0.25 times the number of hours (t), plus the already completed road, which is 9.5.