28 men can finish the job in 60 days. At the start of the 16 day, 5 men were laid off and after the 45th, 10 more men were hired. How many days were delayed in finishing the job? Please explain, step by step.

asked
User Stonean
by
7.7k points

1 Answer

3 votes
Every day one man can do 1 / ( 28* 60 ) = 1 / 1620 of a job.
After 15 days:
( 28 * 15 ) / 1620 = 1 / 4
From the 16 th to the 45 th day:
( 23 * 30 ) / 1620 = 23 / 56
1 /4 + 23 / 56 + ( 33 * x ) / 1620 = 1
14 / 56 + 23 / 56 + 11 x / 560 = 1
140/ 560 + 230 / 560 + 11 x / 560 = 1
370 + 11 x = 560
11 x = 190
x = 190 : 11 ≈ 17.27
17.27 - 15 = 2.27 days
Answer: 3 days were delayed in finishing the job.