Greg planned for his company to make $ 25,000 this month . Instead, they made $18,000 . Calculate the variance .

asked
User Juhi
by
8.1k points

2 Answers

9 votes

Answer:

72%

Explanation:

18,000 / 25,000 = 72% variance. In other words, they made 72% less than they had projected.

answered
User Alphy
by
8.1k points
10 votes

Answer:

The answer is $7,000

Explanation:

did it on acellus

answered
User Brian Syzdek
by
8.0k points