asked 153k views
5 votes
If your company needs to produce 7,800 products by the end of the next 12 weeks, how many products will you need to produce each week to finish on schedule?

1 Answer

6 votes

The company will have to produce at least 650 products each week to achieve 7800 products in 12 weeks


(7800 products divided by 12weeks = 650 products per week)

answered
User Tyanna
by
8.9k points

No related questions found

Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.