asked 93.8k views
5 votes
Project risk events tend to be unlikely __________ a project, but that's also when they tend to be the __________. early in; most costly late in; least costly late in; most costly before the beginning of; most complex at the conclusion of; least complex

1 Answer

5 votes
Project risk events tend to be unlikely early in a project, but that's also when they tend to be the most costly. This is because they are harder to predict. Unpredictable costs end up being the most costly as they are unmitigated.