asked 162k views
2 votes
Paul worked 43 hours at a rate of $7.25 for straight time (40 hours) and time-and-a-half for overtime. What was his total pay?

2 Answers

1 vote
Paul worked 40 hours of his regular pay.
(40 x 7.25 = $290)

Paul worked 3 hours of time and a half.
(3 x 7.25 + 3.625 (half of 7.25) = 10.875)
So 3 x 10.875 = $32.625

$32.625 + $290.00 = $322.62




answered
User Blacktrance
by
8.2k points
5 votes

Answer:

Paul's total pay was $322.63.

Explanation:

Paul worked for 40 hours at a rate of $7.25

and he did 3 hours overtime at a rate of time and a half = 7.25 × 1.5 = $10.875

His total pay = 40(7.25) + 3(10.875)

= 290 + 32.625

= $322.625 ≈ $322.63

Paul's total pay was $322.63.

answered
User CAD Bloke
by
8.3k points

No related questions found

Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.