Work the following pricing problems for services rendered. (Round to tenths.) Labor rate = $7.50 per hour Labor time = 6.5 hours Retail price of parts = $0 Total job cost = $82.00 Overhead rate?

asked
User RaceBase
by
7.7k points

2 Answers

6 votes

that's wrong the answer is 68.2%

answered
User Qakmak
by
8.6k points
5 votes
Overhead cost is the Total Cost minus the cost of all inputs, in this case labor and price of parts. The Overhead Rate is this number divided by total labor hours.
Total Cost: $82.00
Labor Cost: 7.5 x 6.5 = $48.75 -
Price of parts: $0
Overhead Costs: = $33.25
Divided by labor hours ÷ 6.5
Overhead Rate = $5.12
Overhead rate is $5.12