He navy awards a cost-plus-award-fee (cpaf) contract for $265 million to design and develop electronic components for a communications system with a period of performance of 18 months. what reports, if any, must the navy program manager (pm) require the contractor to provide regarding their cost, schedule, and technical performance

asked
User Juggeli
by
7.6k points

1 Answer

6 votes

What reports, if any, must the navy program manager (pm) require the contractor to provide regarding their cost, schedule, and technical performance?

The Navy PM would require submission of an Integrated Program Management Report (IPMR) with formats 1 through 7.