There are 3 people who work full time and are to work together on a project, but their total time on the project is to be equivalent to that of only one person working full time. if one of the people is budgeted for 1/2 of the time and the other person is budgeted for 1/3, what part od the third workers time should be budgeted to this project

asked
User Bijou
by
7.8k points

1 Answer

4 votes
1/2 + 1/3 + x = 1
5/6 + x = 1
x = 1/6
x being the amount of time for the third person. YOU'RE WELCOME :D