What is an auditor's evaluation of a statistical sample for attributes when a test of 50 documents results in 3 deviations if the tolerable rate is 7%, the expected population deviation rate is 5%, and the allowance for sampling risk is 2%?

asked
User TheKRAY
by
8.7k points

1 Answer

3 votes
Answer: The planned assessed level of control risk should be modified because the sample deviation rate plus the allowance for sampling risk exceeds the tolerable deviation rate.