asked 11.6k views
5 votes
In a work breakdown structure, the sequence of tasks in which there is no slack is referred to as:

1 Answer

3 votes
Critical path, the sequence of the tasks where there is no slack. Meaning if one task doesn't start on time because another has not yet been completed, there is no down time and there will inevitably be a delay in the project.
answered
User Ctwhome
by
7.5k points

No related questions found

Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.