asked 70.1k views
1 vote
It takes Brian 15 hours longer to build a model car than it takes John. If they work together, they can build the model car in 4 hours. Using complete sentences, explain each step in figuring out how to determine the time it would take Brian to build the car on his own.

asked
User Tolgap
by
8.1k points

1 Answer

2 votes
1) Let x the time needed by John to complete the job, so
the time needed by Brian to complete the job will be x+15

2) The rate per hour for John to complete the job is 1/x
The rate per hour for Brian to complete the job is 1/(x+15)

3) But the rate per hour to complete the job is 1/4

Hence we have the following equation:

1/x + 1/(x+15) = 1/4 . Reduce to the same denominator and you will get:
4(x+15) + 4x = x(x+15). Solve for x:

x²+7x - 60 = 0 . Quadratic equation. Use the formula to find the roots:

x' = [-b+√(b²-4.a.c)]/2a and x' = [-b-√(b²-4.a.c)]/2a

x' = 5 and x" = -12 (extraneous)

Then John alone he will complete the job in 5 hours
an Brian alone he will complete the job in 20 hours

Both will complete the job in 4 hours

Proof:

1/5 + 1/20 = 5/20 = 1/4