The ________ is a sequence of activities that determine the earliest date by which a project can be completed.

2 Answers

3 votes
The critical path is a sequence of activities that determine the earliest date by which a project can be completed.
answered
User Nuss
by
7.8k points
1 vote

Answer: The correct answer is : The critical path

Explanation: An activity on the critical path cannot be started until the previous activity has been completed. Critical route analysis is the process by which project managers compress the schedule, moving resources, normally changing people from non-critical route tasks to critical route tasks.