asked 178k views
5 votes
If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a container will hold 20 parts, how many containers are required?

1 Answer

6 votes

5 parts per minute times 100 minutes = 500 parts

500/20 = 25 containers are needed

answered
User Phil Haselden
by
9.6k points

No related questions found

Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.