What must a project manager do before creating a dependency schedule?

A. Identify which tasks must be completed by the project manager.
B. Identify which tasks will involve the most teamwork.
C. Identify which tasks can be skipped.
D. Identify which tasks are primary and which are dependent.

2 Answers

0 votes
D. Identify which tasks are primary and which are dependent.
answered
User James Buck
by
7.8k points
4 votes

Answer: The correct answer is : D. Identify which tasks are primary and which are dependent.

Explanation: When a predecessor value is assigned to a task, the new task can only be started once all predecessor tasks have been completed. Work should be divided into manageable tasks. It is also important to estimate the time it takes to complete a task.