Lorek company acquires land for $160,000 cash. additional costs are as follows: removal of shed, $500; filling and grading, $2,000; salvage value of lumber of shed, $120; broker commission, $6,000; paving of parking lot, $15,500; closing costs, $1,000. lorek company should record the acquisition cost of the land as

asked
User Ninj
by
8.2k points

1 Answer

5 votes
$160,000 + $6,000 + $1,000 = $167,000. I don’t believe that the removal of the shed, filling and grading, or paving the parking lot would be considered part of the acquisition itself, so those values are there just to throw you off from the correct answer.