The three key parts of material requirement planning (mrp) are ____.

a. suppliers' invoices, distribution schedules, and inventory records
b. inventory records, trend analyses, and production schedules
c. inventory turnovers, master production schedules, and storage space
d. the master production schedule, the bill of materials, and inventory records
e. aggregate inventory, suppliers' invoices, and bills of laden

asked
User Amdex
by
7.9k points

1 Answer

4 votes
D. the master production schedule, the bill of materials, and inventory records.
That's the correct answer