asked 202k views
4 votes
A _____ cannot be started until one or more other tasks are completed.

a. dependent task
b. concurrent task
c. predecessor task
d. all of the above

asked
User Takahiro
by
8.1k points

1 Answer

2 votes
A dependent task cannot be started until one or more other tasks are completed.
This type of task belongs to a certain project or process and relates to other tasks of the same project or process. The dependent task ensures their interconnection and common direction. It cannot be started until the prerequisite task is completed.

answered
User Roostaamir
by
9.2k points