What conditions must exist for separate contracts to be viable?

asked
User SPaz
by
7.9k points

1 Answer

3 votes
The owner must be an in house CM or construction engineer to administer the contracts. CM is established as an independent contractor. The CM is responsible to the owner to complete the project by the established substantial completion date and within the agreed budget. The CM must compensate the owner when the construction does not satisfy the established standards of performance for a project.