For Jason, it takes 3 hours to clean the attic. However, Sara takes 6

hours to complete the same job. If working together, how long would they take?

asked
User Cystbear
by
8.0k points

2 Answers

10 votes

Answer:

2

Explanation:

I think bc I just divide im guessing

answered
User Berly
by
7.2k points
10 votes
I think its the correct answer :)