To complete the first setup on a new machine took an employee 300 minutes. using an 88???% cumulative average minus time learning curve indicates that the second setup on the new machine is expected to take??? ________.

a. 132 minutes

b. 228 minutes your answer is correct.c. 282 minutes

d. 264 minutes