The number of hours required to do a job varies inversely as the number of people working. It takes 8 hours for 4 people to paint the inside of a house. How long would it take 5 peole to do the job?

1 Answer

6 votes

Answer: it will take 5 people 6.4 hours to do the work.

Explanation:

The number of hours required to do a job varies inversely as the number of people working. Let h represent the number of hours required to do the job. Let p represent the number of people working. Therefore,

h is inversely proportional to p

Introducing a constant of variation, k, it means that

h = k/p

It takes 8 hours for 4 people to paint the inside of a house. Therefore

8 = k/4

k = 8×4 = 32

The formula becomes

h = 32/p

To determine how many hours it will take 5 people to do the work, we will substitute p = 5 into the formula. It becomes

h = 32/5 = 6.4 hours

Related questions

asked Aug 19, 2018 168k views
Vladimir Dyuzhev asked Aug 19, 2018
by Vladimir Dyuzhev
7.7k points
2 answers
5 votes
168k views
2 answers
4 votes
195k views
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.