Calculator To determine how to crash activity times,

a.shortest times with crashing must be known.
b.normal activity costs and costs under maximum crashing must be known.
c.realize that new paths may become critical.
d. All of these choices are correct.

asked
User Siliarus
by
8.6k points

1 Answer

4 votes

Answer:

To determine how to crash activity times:

d. All of these choices are correct.

Explanation:

To determine and calculate the crash activity times:

  • We should know the shortest times with crashing.
  • We should know the normal activity and costs under maximum crashing.
  • We should realize that new paths can become critical.