asked 99.6k views
1 vote
You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?

a. Quantitative risk analysis
b. Risk audits
c. Requested changes
d. Qualitative risk analysis

asked
User Blueyed
by
8.3k points

1 Answer

5 votes

Answer: Requested Changes is an output of Risk monitoring and control.

Explanation: In risk monitoring and control, the progress of a project being executed is tracked, evaluated, reviewed, and reported.

Requested changes is one of the outputs of risk monitoring and evaluation that involves making a formal demand for a change to be effected in the project.

answered
User Mefathy
by
7.5k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.

Categories